Shuaibah IWPPShuaibah IWPP is in the process of being decommissioned and replaced by a reverse osmosis seawater desalination plant with a capacity of 600,000 m3/day.
Saudi Arabia
9,188
30.00%
900
880
Oil/MSF
Q1 2010
Shuaibah Expansion IWP
Saudi Arabia
874
30.00%
-
150
SWRO
Q4 2009
Petro-Rabigh IWSPPPetro-Rabigh IWSPP is a captive plant producing 29,520 tonnes of steam per day in addition to power and water for the offtaker. Petro-Rabigh IWSPP includes Petro-Rabigh (Phase 2) IWSPP.
Saudi Arabia
8,155
99.00%
520
189
Oil/SWRO
Q2 2008Q2 2008 was the PCOD for Petro-Rabigh IWSPP. Petro-Rabigh (phase 2) IWSPP PCOD was Q1 2018.
Marafiq IWPP
Saudi Arabia
11,561
20.00%
2,744
800
Natural Gas/ MED
Q4 2010
Rabigh IPP
Saudi Arabia
9,398
40.00%
1,204
0
Oil
Q2 2013
Barka 1 IWPP
Oman
1,556
41.91%
427
91
Natural Gas/ MSF
Operational when acquired in Q3 2010
CEGCO AssetsCEGCO includes four assets of which two are renewable (wind) assets.
Jordan
1,759
40.93%
692
0
Natural gas
Operational when acquired in Q3 2011
Hajr IPP
Saudi Arabia
10,219
22.00%
3,927
0
Natural gas
Q1 2015
Barka 1 Expansion IWP
Oman
199
41.91%
-
46
SWRO
Q2 2014
Noor I CSP IPP
Morocco
3,153
73.13%
160
0
CSP parabolic
Q1 2016
Bokpoort CSP IPP
South Africa
1,939
20.40%
50
0
CSP parabolic
Q1 2016
Rabigh 2 IPP
Saudi Arabia
5,854
50.00%
2,060
0
Natural gas
Q1 2018
Kirikkale CCGT IPPKirikkale is a merchant-market asset.
Turkey
3,488
69.60%
950
0
Natural gas
Q3 2017
Khalladi Wind IPP
Morocco
655
26.01%
120
0
Wind
Q2 2018
Barka 1 Phase II Expansion IWP
Oman
298
41.91%
-
57
SWRO
Q1 2016
Noor II CSP IPP
Morocco
4,125
75.00%
200
0
CSP parabolic
Q2 2018
Noor III CSP IPP
Morocco
3,233
75.00%
150
0
CSP tower
Q4 2018
Shuaa Energy PV IPP
UAE
1,222
24.99%
200
0
PV
Q1 2017
Salalah 2 IPP - Existing
Oman
629
27.00%
273
0
Natural gas
Operational when acquired in Q2 2015
Salalah 2 IPP - Greenfield
Oman
1,687
27.00%
445
0
Natural gas
Q1 2018
Ibri IPP
Oman
3,683
44.90%
1,509
0
Natural gas
Q2 2019
Sohar 3 IPP
Oman
3,686
44.90%
1,710
0
Natural gas
Q2 2019
Zarqa IPP
Jordan
1,834
60.00%
485
0
Natural gas
Q3 2018
NOOR PV1 IPPNOOR PV 1 IPP includes three assets.
Morocco
788
75.00%
135
0
PV
Q4 2018
Mafraq PV IPP
Jordan
265
51.00%
50
0
PV
Q4 2018
Shuaibah 2 IWP
Saudi Arabia
1,155
100.00%
-
250
SWRO
Q2 2019
Risha PV IPP
Jordan
254
51.00%
50
0
PV
Q4 2019
BenBan 1
Egypt
281
32.81%
50
0
PV
Q3 2019
Ben Ban 2
Egypt
300
32.81%
50
0
PV
Q3 2019
Ben Ban 3
Egypt
113
18.05%
20
0
PV
Q3 2019
Salalah IWP
Oman
600
50.10%
-
114
SWRO
Q1 2021
Rabigh 3 IWP
Saudi Arabia
2,576
70.00%
-
600
SWRO
Q4 2021
Al Dur Phase II IWPP
Bahrain
4,125
60.00%
1,500
227
Natural Gas/ SWRO
Q2 2022
UAQ IWP
UAE
2,988
40.00%
-
682
SWRO
Q3 2022
Ibri 2 PV IPP
Oman
1,481
50.00%
500
-
PV
Q3 2021
Jazan IGCCIn addition to power, Jazan IGCC also produces steam: 585,000 tonnes/hour, and hydrogen: 184,000 Nm3/hour.
Saudi Arabia
45,000
25.00%
3800
-
Oil
Q4 2021
Sakaka PV IPP
Saudi Arabia
1,133
70.00%
300
-
PV
Q2 2020
Total
149,449
25,182
4,084
Project name
Country
Total investment cost (MSAR)
ACWA Power effective share
Contracted power (MW)
Contracted water (000’ m3 /day)
Technology
PCOD (actual / expected) / Status
UNDER CONSTRUCTION
Hassyan IPPConverted from primary coal to primary natural gas asset in Q1 2022.
UAE
12,140
26.95%
2,400
0
Natural gas
Q3 2023
Noor Energy 1
UAE
17,145
24.99%
950
-
CSP
Q4 2023
Taweelah IWP
UAE
3,278
40.00%
-
909
SWRO
Q2 2023
Jazlah IWP
Saudi Arabia
2,468
40.20%
-
600
SWRO
Q1 2023
Shuaa Energy 3Following the Company’s partial divestment, subject to the completion of the conditions precedent of the SPA, effective shareholding of the Company in Shuaa Energy 3 will reduce to 12.24%.
UAE
2,108
24.00%
900
-
PV
Q1 2023
Sirdarya CCGT IPP
Uzbekistan
3,814
51.00%
1,500
-
Natural gas
Q3 2023
Kom Ombo
Egypt
619
100.00%
200
-
PV
Q3 2023
Redstone CSP IPP
South Africa
2,715
49.00%
100
-
CSP tower
Q4 2023
Sudair PV IPP
Saudi Arabia
3,465
35.00%
1,500
-
PV
Q4 2024
Red Sea Project
Saudi Arabia
5,966
50.00%
340
33
PV, BESS, ICE, RO, district cooling
Q4 2023
Shuaibah 3 IWP
Saudi Arabia
3,113
68.00%
-
600
SWRO
Q2 2025
Bash Wind IPP
Uzbekistan
2,588
100.00%
500
-
Wind
Q1 2025
Dzhankeldy Wind IPP
Uzbekistan
2,468
100.00%
500
-
Wind
Q1 2025
Total
61,883
8,890
2,142
Capacity of assets under construction that have achieved partial COD
Project name
Country
ICOD
Online capacityCumulative total capacity that is online as at the ICOD date.
Power (MW)
Water ('000 m3 /day)
Shuaa Energy 3
UAE
Oct-22
600
-
Taweelah IWP
UAE
Jun-22
-
455
Noor Energy 1
UAE
Dec-21
217
-
Hassyan IPP
UAE
Sept-21
600
-
Total
1,417
455
Project name
Country
Total investment cost (MSAR)
ACWA Power effective share
Contracted power (MW)
Contracted water (000’ m3 /day)
Technology
PCOD (actual / expected) / Status
ADVANCED DEVELOPMENT
Azerbaijan Wind IPP
Azerbaijan
1,073
100.00%
240
-
Wind
PPA signed
Neom Green HydrogenWhen commissioned, the project will produce 600 tonnes of clean hydrogen per day and 1.2 million tonnes of green ammonia per year.
Saudi Arabia
31,875
33.33%
3,883
-
PV+Wind
PPA signed
Shuaibah PV IPP
Saudi Arabia
1,219
50.00%
600
-
PV
PPA signed
Kungrad 1 Wind IPP
Uzbekistan
3,998
100.00%
500
-
Wind
PPA signed
Kungrad 2 Wind IPP
Uzbekistan
2,501
100.00%
500
-
Wind
PPA signed
Kungrad 3 Wind IPP
Uzbekistan
2,501
100.00%
500
-
Wind
PPA signed
Suez Wind
Egypt
5,625
75.00%
1100
-
Wind
PPA signed
Nukus Wind IPP
Uzbekistan
404
100.00%
100
-
Wind
PPA signed
Ar Rass PV IPP
Saudi Arabia
1,688
40.10%
700
-
PV
PPA signed
Saguling Floating PV IPP
Indonesia
225
49.00%
60
-
PV
Preferred Bidder
Singkarak Floating PV IPP
Indonesia
188
49.00%
50
-
PV
Preferred Bidder
Laylaa PV IPP
Saudi Arabia
394
40.10%
80
-
PV
PPA signed
Shuaibah 2 PV IPP
Saudi Arabia
6,563
50.00%
2,060
-
PV
PPA signed
Total
58,252
10,373
Total investment cost (MSAR)
Contracted power (MW)
Contracted water (000’ m3/day)
Total operational assets
149,449
25,182
4,084
Total assets under construction
61,883
8,890
2,142
Total assets in the advanced development stage
58,252
10,373
GRAND TOTAL
269,584
44,445
6,226
For further details on our assets kindly visit our website